White Hart Bridge Deck Replacement, Essex Highways

Essex Highways attended a meeting of the Parish Council on the 4th November 2021 to present findings and works required to replace the deck on the White Hart Bridge.  Works are scheduled to commence in April 2022. A 16 week traffic control will be in operation (manual during peak hours, automatic traffic out of hours). Road will be kept open, single traffic only.  Work is expected to last 4/5 months could be longer if additional works required.

Essex Highways White Hart Bridge Deck Replacement